19 нояб. 2012 г. · The amount of hours worked is multiplied by the Dollar amount, so for example, if the person worked 5 hours and the Dollar amount is $10 then I would need $50 ... |
8 нояб. 2011 г. · To get a total pay cost, assume hours in A2, Pay Rate in B2, and your total Pay Cost in C2: C2: =A2 * 24 * B2 |
26 февр. 2018 г. · I am looking for a formula to calculate hours worked by hourly rate. I also need to work out the format the answer is to be written. |
14 дек. 2012 г. · In a query based on the table, add a calculated column like this: Cost: [Duration]*[PricePerMinute]*1440 where Duration is the time in minutes and ... |
18 мая 2020 г. · Hello, I have a time tracking spreadsheet I use for calculating hours worked and then multiplying those hours by a billing rate. |
8 нояб. 2017 г. · 1. How to divide a time (in time format; hh:mm:ss)) by a number and vice versa 2. How to multiply a time by a number. |
26 сент. 2014 г. · Simply multiply the summed time by the rate you will get the wrong answer and to understand why you have to understand how times are stored in Excel. |
4 мар. 2013 г. · To convert duration in h:mm:ss or h:mm you need to multiply it with 24*60 to get minutes. When you multiply it again by 2 you get the multiples of 30 seconds. |
27 июл. 2016 г. · I have a labour rate of £22 per hour in a cell and an output rate of 0.15 in another. When multiplying these 2 figures together the answer should be £3.30 ... |
28 янв. 2016 г. · I have a table with a starting number, and for each following cell I need that number to be multiplied by a decreasing amount. |